Tasks are showing as completed on the plan but within Data Engine they are showing as Ready To Start.


The functionality has been enhanced in Orchestrate version 7.74. Please upgrade to this version or above.
​
​

Please be aware that the reports in Analytics data must not be pulled directly from the orc_Tasks table, where the status is wrong, instead you should use the table report.Analytics_TasksWithBaselineInfo