How can I lock a jobs production date so that even if the production date of an other job on the same machine slips it does not push out the start date of the priority job; it would be re-scheduled to after the priority job.
How can I unlock all the tasks?
You can lock single tasks via the following steps:
1. Double-click the relevant task from the Gantt Chart
2. Tick Locked from schedule tab of Edit Tasks (left hand pane)3.
3. Click Apply
You can lock a group of tasks over a period of time via the following steps:
1. Select edit
2. Select in date range
3. Select relevant options e.g. tasks - finish, date options - between dates
4. Click OK
5. Select edit tasks
6. Ticked locked
7. Click apply
You can unlock all tasks by completing the following steps:
1. Select Edit
2. Select all (or press Ctrl + A)
3. Select edit tasks from the left hand pane
4. Scroll down and untick Locked
5. Click apply