Lateness figure is too high when planning works orders

Written by Charnjit Singh Dharival

Run an algorithm and some works orders plan too far ahead. The lateness figure is too large e.g. -20.


Orchestrate searches all planned tasks (including planned archived tasks) of a given works order and determines the Lateness Days by comparing the largest FinishDate and DeadlineDate.

Delete any archived tasks that are no longer required:

  1. select planning

  2. archive completed tasks

  3. Highlight the relevant tasks and click Edit

  4. Highlight the rows and click Delete Rows

  5. Click OK

If archived tasks that finish before their deadline date are being read by the planning logic, please start a conversation on the Access Community Portal. How to contact Support via the MyAccess Portal | Orchestrate Help Centre