Split tasks

Written by Charnjit Singh Dharival

How do you split tasks on the plan?


If you select any tasks that is not running on the plan, right-click them and select Split Task.

You can split the task by time or Quantity.

The new task can have the following options:-

  • Inherit setup time from the original task

  • set setup time to zero

  • split material requirements by task quantity ratio

  • transfer or don't transfer material requirements to the new task

NOTE: choosing transfer or don't transfer option will cause material requirements to become static values.

  • split productions by task quantity ratio

  • transfer or don't transfer productions to the new task

NOTE: choosing transfer or don't transfer option will cause production to become static values.

Did this answer your question?