Cannot close gaps between certain tasks or works orders

Written by Charnjit Singh Dharival

When trying to close gaps between certain tasks on the Gantt chart, it does not work for certain tasks or works orders.


Solution 1

Missing quantities entered in the labour resources shift patterns can cause this issue. Please complete the relevant steps to rectify this fault:

  1. Select Resources

  2. Select Default Shift Pattern Assignment

  3. Select Quantity Adjustment tab

  4. Select relevant resource and shift pattern

  5. Click Edit

  6. Enter quantities for relevant weekdays

Solution 2

Another cause is min offset values in task dependencies. Please complete the following steps make close gaps work:

  1. Right click the relevant task on the plan

  2. Select Edit Task Dependencies

  3. Select Predecessor tab

  4. Remove the figure in the Min Offset field

  5. Go to Successor tab

  6. Remove the figure in the Min Offset field

  7. Click Apply

The Min Offset means that the tasks cannot be planned closer together than the min offset value.
​
If you wish to plan with a min offset, but be able to drag the tasks closer together, or close gaps to remove the offset, then there is a feature called Secondary Offsets from system settings that needs to be turned on. Please complete the following steps:

  1. Log into Orchestrate System Manager

  2. Select File

  3. Select System Settings

  4. Select planning tab

  5. tick On under Enable Secondary Offset

  6. Click OK

Note: Log out and back into Orchestrate for the settings to take effect.

Solution 3

A workaround if the above solutions do not work is to tick unconstrained on the relevant resource. The task may close the gap and overload the resource, which indicates there are sufficient tasks on that specific area of the resource already:

  1. select resources menu

  2. select relevant resource and click edit

  3. tick unconstrained

  4. click OK

Solution 4

If you have upgraded Orchestrate from version 7.66 or above, tick the following options and unplan and re-plan the relevant task(s) or works orders:
​

  1. Select Tools

  2. options

  3. planning (tab)

  4. sub-heading 'Search For Unpegged Material' now has two options that can be ticked:-

  5. check availability of made items when planning

  6. check availability of purchased items when planning

Solution 5

Certain tasks don't close gaps because it was marked as started (In Progress) within the data import, from the ERP system. Close Gaps does not affect tasks with a status of 50 (Started) or above.