Press Close Gaps and tasks moves to a different resource or moves to match the start of the previous task

Written by Charnjit Singh Dharival
  • When I click Close Gaps, the tasks moving to different resources. Yet, when I try to drag the task to another resource, the warning kicks in to prevent the drag.

  • I have an issue where I have two jobs with a gap between them due to insufficient resource. I use overloads on the second task and then close gaps. The second the job will move to match the start of the previous task rather than just closing the gap to the end of the first task.


Please complete the following steps:

  1. Launch and log into Orchestrate System Manager

  2. Click File, System Settings

  3. Click the Planning tab

  4. Under the option Close Gaps Replan, select Off

  5. Log out and back into the plan. The close gaps will work as normal.

Note: The option Close Gaps Replan, only affects primary resources and not secondary resources