Some tasks are scrambled and overloaded some resources when planning works orders

Written by Charnjit Singh Dharival

Cannot plan tasks correctly after a data import or saving the plan.
​
Some tasks overloaded on the resource when planning the second works order.


The task shuffling logic maintains a sequence of the tasks to preserve the sequence of tasks. The Plan.ShuffleTasks logic has been refactored in Orchestrate version 7.64
​
The saving plan functionality has been enhanced in Orchestrate version 7.66 to prevent the data being out of synch.

Further enhancements have been made in Orchestrate version 7.71 and hotfix 20. Please upgrade to this version or above.