Skip to main content

Successor task dependency disappear after changing work start date

Written by Charnjit Singh Dharival

Task dependencies should not be removed without user input by the system as that is currently what planners are seeing. The planning logic removes task dependencies is the overall issue, because the ones it breaks is what breaks the order of tasks. Planners are working are on reducing the complexity of our dependencies to mitigate the issue.


The functionality has been enhanced in Orchestrate version 7.82 Hotfix 40. Please upgrade to this version or above.

Did this answer your question?