Tasks overload when dragging and dropping tasks onto the main resource

Written by Charnjit Singh Dharival

Unable to drag and drop tasks on the main resource. Users could place a set of tasks on the main resource, where needed, to clean the piece of equipment. This caused task overloading in the main resource. Then we would unlock all the tasks on this resource and pull them back and they would go to the correct spot to align with the main resource. Now, we can't do that. They remain out of sync. Not sure if there was a background setting that was allowing us to have that functionality.


The plan shuffling logic has been enhanced in Orchestrate version 7.70 Please upgrade to this version or above.