When moving a task from a production line to another production line, the linked task on the constraint resource can disappear or can it be automatically moved to the constraint resource linked the other production line resource?
For example, a task on resource PROD1 (production line) moves to resource PROD2 (another production line). The linked task is current on resource CONSTRAINT1. This linked task needs moving automatically to CONSTRAINT2 (which is part of production line PROD2).
This request is not supported by the current planning logic. Please drag both tasks to the relevant resource. This functionality cannot be automated.