The works order start date from ASC not in synch with task start date on the plan

Written by Charnjit Singh Dharival

The Works Order Start Date & Date/Time Required have not been correctly updated by Task / operation start and due dates when I run the export to ASC.


The manufacturing routes have been changed and that is the reason the offending works orders have not behaved as expected with the start dates. For example, the part may have changed resource recently. It is entirely possible that the resource has been changed in between times.