Add some downtime to a resource with a unit value and cannot drag task past this section

Written by Charnjit Singh Dharival
  • Added some downtime to a resource (e.g. two hours) but the task cannot drag past the designated downtime period.

  • The downtime is not working.

  • Enter 0 or 1 in the units?


Downtime works like normal shift pattern non-working time. The cause of the issue is with how we are entering the downtime. Do not enter any negative or positive values. You enter a value for how many units are available at that time. In this instance, you enter 0:

  1. Select resources

  2. Overtime / Downtime

  3. Enter the resource, duration etc.

  4. Within units, enter 0 and not -1