Steps you can take to resolve the process definition error that occurs when Same Resource and Allow Task Overlaps are used together on a multi-capacity resource.

Written by Arthur Ashdown

You may see the following error when planning a works order:

Order code [order code]
​
Error in process definition, process [process name] Resource [resource name] Same resource relationship type cannot be used on multiple capacity resources. Remove the same resource marker from the dependency with op 2 or remove the task overlaps option on the resource [resource name].


Why this happens

This error occurs because Allow Task Overlaps and Same Resource are switched on at the same time on a multi-capacity resource. These two options are not compatible with each other.

A multi-capacity resource is one where the units available is 2 or above. This applies when:

  • You click Edit from the Resources menu and the units available is set to 2 or above.

  • A labour resource has a quantity adjustment higher than 1 from the default shift pattern assignment.

The Same Resource relationship type can only be used on a resource with a maximum of 1 unit available. Same Resource tasks cannot be assigned to a resource where Allow Task Overlaps is ticked and the units available is 2 or above.


Resolution

To resolve this error, you need to do one of the following on the relevant process or resource:

  • Remove the Same Resource marker from the dependency on the relevant process operation step.

  • Remove the Allow Task Overlaps option on the resource mentioned in the error.

📌Note: Same Resource tasks can be assigned to resources where Allow Task Overlaps is not ticked, regardless of the number of units available.