Exported Orchestrate into FactoryMaster and it doesn't seem to be pulling the correct purchase order dates through.
The following dates are exported between Orchestrate and FactoryMaster:
FactoryMaster | Orchestrate |
Date Placed | Release Date |
Date Required | Not Used |
Date Promised | Deadline Date |
Date Expected | Arrival Date |
The dates of the Purchase Order (PO) tasks might be different from the dates of the purchase orders, as Orchestrate takes lead time into consideration. Since there are leadtimes for the items, Orchestrate will factor them in when calculating the PO task dates. If the lead times have already been included in the POs in FactoryMaster (FM), the lead times of the purchased items should be set to 0 when coming into Orchestrate. The functionality has been enhanced in Orchestrate version 7.79 or above. Please upgrade to this version or above.