The task from the sub-works order is not planning before the associated task of another sub-works order

Written by Charnjit Singh Dharival

The associated operation,sub-task, is not planning before the correct main task for sub works orders.


The problem occurs because there is no link specified on the import between the tasks mentioned. The integration has been enhanced in FactoryMaster version 20.10.06 to resolve this issue. Please upgrade to this version or above.
​
If you are not in a position to upgrade, add time to MA Lead time in the stocked part for each level in FactoryMaster. The works orders will then import correctly into Orchestrate.
​
If the above does not resolve the issue, please raise a new case online and reference the title of this article.
​