The non-working time on the Gantt Chart is no longer visible.
There are no grey vertical bars in the background of the Gantt Chart.
The functionality has been enhanced in Orchestrate version 7.69. Please upgrade to this version or above.
β
If you are not in a position to upgrade yet, please change the Plan Start Date and Time to resynch the plan with the database, via the following steps:
Select file
Plan properties
Change the date
If this cannot be actioned, we can resynch the default planning range from the database. Please raise a new case online and reference the title of this article.