There is an option called 'Shuffle Plan After Unplanning' in System Manager. I would like to understand what this system setting does to the plan when turned on.
This system setting Shuffles the plan automatically after unplanning works orders or tasks. Task shuffling is to do with dragging tasks and other tasks within the Gantt Chart. Dragged task behaviour has been enhanced. For example, Reduce Waiting Time was inefficient. Problem with shuffling logic when (MaxOffset - MinOffset) < (PredecessorTask.WorkTime + SuccessorTask.WorkTime). This functionality was enhanced and implemented in Orchestrate version 7.64.