User unable to import the release date from FactoryMaster. When planning works orders, the release date is missing
Please complete the following steps in FactoryMaster:
Select production
Works order enquiry
Hit enter and select the relevant works order
Press F5 to zoom into the Required column and enter the Earliest Start Date.
This imports the works order into Orchestrate has the Release Date. The works order then plans to the earliest start date on the Gantt Chart. The release date is also represented within Edit Tasks of the plan; in the field: Start no earlier than.