Planner's colleague can't see the links between the purchase order, works order and sales order from material dependencies, when selecting a task from the Gantt Chart. Planner can open the plan from there login and see the material dependencies for the relevant works order fine.
Please select the relevant works order from the order planner (not double-clicking the task from the Gantt Chart) and then the material dependencies will show the correct information.