User can see tasks move on the schedule after they update actuals, as well as completed tasks showing up in future schedules.
The actuals seem to be changing the setup, start, and finish dates on the gantt chart.
The Actuals functionality has been enhanced in Orchestrate version 7.77 to prevent creating multiple completed actuals when pressing the appply button multiple times. This was also affecting dates. Please upgrade to this version or above.