Explanation of how the item production rate calculates.
It is important to know and understand the way in which Orchestrate makes a decision with regards to what rate to use when planning certain tasks, using the item production rates.
When it comes to deciding what rate is being used to plan a task, based on the Rate Table, the following principles are being applied.
Latest rate (based on from date) that is found, that matches the given criteria will be returned in the following sequence:
Order Of Selection | Resource | Item | Op Code |
1 | Specified | Specified | Specified |
2 | Specified | Specified | Any |
3 | Specified | Any | Specified |
4 | Specified | Any | Any |
5 | Any | Specified | Specified |
6 | Any | Specified | Any |
7 | Any | Any | Specified |
8 | Any | Any | Any |