Skip to main content

The Tasks Overview 'Components Ready Date' is blank or Plan Ready Date is missing from the sales order planner

Written by Charnjit Singh Dharival
  • Select a order view and the task attribute 'Task - Components Ready Date' is empty, after running a data import.

  • The 'Plan Ready Date' is no longer populated within the Sales Order Planner.


Please complete the following steps after logging into Orchestrate and opening the plan:

  1. Select Tools

  2. Options

  3. Planning tab

  4. Tick Availability of Made Items when Planning

  5. Save the plan

  6. Log out, log back in and reopen the plan

Did this answer your question?