I have planned operations associated with multiple and incorrect tasks. The same Works Order and Operation appearing on resources where they shouldn't.


The view shows tasks on primary as well as secondary resources, thus, two entries will be shown if a task is scheduled on a primary resource, as well as a secondary resource. Look at the Gantt Chart and you will notice that the relevant Op Step is scheduled on two resources.
​
So, the tasks have secondary resources. Please check which task op steps are supposed to be on the labour resources, which ones are supposed to be on the machine resource and which ones are supposed to be on both machine and labour resources.
​
If you would like to see this information from the database, Please run the below SQL command on the Orchestrate database to see the relevant task on the secondary resource:

SELECT * FROM wf.orctmp_TaskSecondaryResources WHERE JobCode LIKE '%works order number%'