Close Gaps and task shuffling break dependency links and re-sequence unconnected tasks, causing plan-wide cascade
Close Gaps and moving tasks on the Gantt chart now respect dependency links that are already broken. If a plan already had broken dependency links (a task scheduled before the task it depends on had finished), Close Gaps could ignore those links. So could moving a task to a new position on the Gantt chart, which uses Close Gaps. They could then schedule more tasks before their predecessors and move tasks from unrelated orders on the same resource across the plan. This happened most often on resources that can run only one task at a time. Both now take these links into account. Where the tasks can be moved, the dependent task is moved later so the link is restored, and tasks from unrelated orders are no longer re-sequenced.
Only the tasks involved in the operation are affected. Broken links elsewhere in the plan stay as they are until you run Close Gaps on those orders. Locked tasks are not moved, so a broken link between locked tasks stays broken. On plans whose dependency links are intact, behaviour is exactly as before.
Orchestrate breaks dependency rather than shuffling
Dragging a group of operations to a later time could leave a dependent operation on another resource at its old position, breaking the dependency. Orchestrate now moves the dependent operation forward when analysing plan and implications, so the dependency is kept.