How can I revert the current plan back to the beginning?
I need to create a new plan.
Please log into Orchestrate and complete the following steps:-
Select File
New Plan
Check the following date fields
plan start date and time: the date represents current time on plan
the status date and time: the date which represents when stock was last updated
planning start date and time: the earliest date we can add orders to the plan from
4. Click OK
The existing resources, items, works orders etc. from the current plan will be carried across to the new plan. You cannot revert the existing current plan back to ground zero. There are too many database tables containing data referencing other tables, which affects data integrity. For example, task dependencies table linked to pegging link tables. You have to manually update the stock inventory.