When a planner selects a different view and then goes back to the original view, the number of listed works orders decreases.
In the View Manager (the camera button on the left of Saved Views), from the Saved Views drop down, select the views in question. A example is described below:
View 1 - The date range is set to Zoom All.
View 2 - Has a No Change to Date Range (meaning that whatever the date range is when selecting this view, it doesn't automatically change the date range when this view is applied).
View 3 - The date range is set to Zoom All.
Select View 2 then set the Date Range to Zoom All
Click Save.
Note: the Zoom All means that it scans the selected resources within that view and it creates a date range to cover all tasks for those resources. The selected resources can be viewed either from the View Manager for a given view, or by changing the Work List to the Gantt Chart. When the view is selected and the Legend is visible, you see the date range for that view.