Skip to main content

Update process but the additional attributes within the process details are not updating

For help adding tasks to existing works orders,but additional attributes within process details are not updating when updating the process

Written by Emma

Date/Time attributes being saved as 30-Dec-1899 00:00 when running Update Process on a process with tasks that have blank/NULL date values now works. It also sets any existing process step attributes that have a values of 30-Dec-1899 00:00 to be NULL (blank) instead. The functionality has been enhanced in Orchestrate version 7.78. Please upgrade to this version or above.

Attributes do not have a way of marking them as updated/excluded. If system parameter EnableUpdateProcessStepAttributeValues is enabled, all task attributes values will update their corresponding process step attribute values as they did previously.


Need further help?

Please contact support with the information above. We will be happy to help!!